Delay Notes
Project Delay Tracking & Root Cause Analysis
| Date | Duration | Work Affected | Cause of Delay | Critical Path Impact | Action Taken | Status |
|---|---|---|---|---|---|---|
| 04 May, 2023 | 4 Hours | Concrete Pouring | Machine Breakdown | Yes | Called mechanic immediately. Rented backup mixer. | Logged |
| 01 May, 2023 | Full Day | All External Work | Heavy Rainfall | No | Internal finishing work prioritized. | Mitigated |