Project Milestones
Key Milestones: City Center Plaza
-
15 Oct
Excavation Finished
Main site excavation completed and approved by engineer.
Achieved -
10 Nov
Foundation Poured
All footings and main foundation slab completed.
Achieved -
05 Dec
Ground Floor RCC
Casting of ground floor pillars and roof slab.
In Progress -
20 Jan
Main Structure (Top Out)
Completion of the final structural floor.
Upcoming
Detailed Milestone List
| Milestone Name | Target Date | Status | Payment Tied | Completion Date | Action |
|---|---|---|---|---|---|
| Excavation & Shoring | 15 Oct, 2023 | Achieved | $50,000 | 14 Oct, 2023 | |
| Foundation Slab | 10 Nov, 2023 | Achieved | $80,000 | 12 Nov, 2023 | |
| 1st Floor Casting | 05 Dec, 2023 | In Progress | $45,000 | - | |
| Brickwork & Plastering | 15 Feb, 2024 | Upcoming | $60,000 | - |