Project Milestones

Key Milestones: City Center Plaza

  • 15 Oct
    Excavation Finished

    Main site excavation completed and approved by engineer.

    Achieved
  • 10 Nov
    Foundation Poured

    All footings and main foundation slab completed.

    Achieved
  • 05 Dec
    Ground Floor RCC

    Casting of ground floor pillars and roof slab.

    In Progress
  • 20 Jan
    Main Structure (Top Out)

    Completion of the final structural floor.

    Upcoming
Detailed Milestone List
Milestone Name Target Date Status Payment Tied Completion Date Action
Excavation & Shoring 15 Oct, 2023 Achieved $50,000 14 Oct, 2023
Foundation Slab 10 Nov, 2023 Achieved $80,000 12 Nov, 2023
1st Floor Casting 05 Dec, 2023 In Progress $45,000 -
Brickwork & Plastering 15 Feb, 2024 Upcoming $60,000 -